| Title | DA commits to extend electricity to Barbari and Megog CHPS compounds. |
|---|---|
| Status | Success |
| Project | GPSA – Making the budget work for Ghana |
| PM&E networking centre | Upper East |
| District | Bawku |
| Commitments made or secured | DA commits to extend electricity to Barbari and Megog CHPS compounds. |
| Stakeholder responsible | MMDAs |
| Commitment platform | Policy dialogue meeting |
| Commitment level | District |
| Commitment period | 2018 |
| Current status of commitment | Electricity has beeconnected to the 2 facilities |
| Specific change resulting from commitment | |
| Change evidence |
Citizens budget input
| Citizens inputs into the budget | |
|---|---|
| Stakeholders who raised issues | |
| Level at which issues were raised | n/a |
| Current status of input issues | |
| Specific change | |
| Change evidence |
Meta
| ID | 4189 |
|---|---|
| Interactions | No interactions |
| Added on | 2018-09-14 |
| Added by | jonathan@sendwestafrica.org |
| Last modified | 2018-10-19 |
| Last modified by | jonathan@sendwestafrica.org |
Leave an update/comment